FULL-PU RUNNING TRACK SYSTEM

  EPDM Brodcast or Spraycoat Top Cover With EPDM
The base layer consists of two-component polyurethane, followed by SBR rubber, a middle Layer of two component polyurethane/SBR, and a top Layer of flow-applied Layer of identically pigmented polyurethane. Finally, the track is broadcast with EPDM rubber or spray special colorful spray-coat material mix with EPDM rubber. The layout, track Lines and event markings are in accordance with the latest edition of the IAAF rules and regulations.

Main Construction Steps

  • Primer and Full-PU bottom Layer coating.
  • Full-PU body layer coating by two times.
  • Full-PU surface layer coating with EPDM broadcast or Spray-coat Layer on top.

 

    Specification

 

Primer Layer (Concrete) :

Seal Layer (Asphalt) :

 

PU Binder Recycle Rubber Granule

Latex Seal Layer Material (add sand and cement)

 

Bottom Layer :

 

Red Full-PU Material

Rubber Granule (Optional, 2-4mm)

 

Middle Layer :

 

Red Full-PU Material
Rubber Granule (Optional, 2-4mm )

 

Surface Broadcast Layer :

 

Red Full-PU Material

Red EPDM Granule (1-4mm)

 

Surface Spray-coat Layer :

Red PU Spray-coat Material

Red EPDM Granule (0.5-2mm,1-3mm,1-4mm)

 

Surface Self Texture Create :
Spray-coat Layer :

 

Red PU Self Texture Create Material

Color Options :